City Sewers Current Construction
Willow Glen Road and Nichols Canyon Road Sewer Project
This sewer pipe rehabilitation project began in spring 2008 in the Hollywood Hills The approximate boundary of the project is Mulholland Dr. on the north, Cahuenga Dr. on the east, Oceanus Dr. on the west, and Hillside Ave. on the south.
QUICK FACTS
- About 3.25 miles of eight-inch sewer pipe will be rehabilitated, or removed and replaced.
- Three maintenance holes will be built and seven existing maintenance holes will be repaired.
- Construction period: spring 2008 through summer 2009. Weather or other circumstances could shift the work schedule.
- Construction will generally take place Monday through Friday, from 7:00 a.m. until 4:00 p.m., and on major streets from 9:00 a.m. until 3:00 p.m., to minimize traffic impacts.
- Estimated Cost: $2.4 million.
- Construction methods will include sewer pipe lining (rehabilitates defective sewers without excavation and surface disruption), and sewer pipe removal and replacement (performed by “open cut” or trenching, a method that is typically used where sewers are shallow).
- In order to minimize disruption in the streets, most of the construction work at each location will be completed in about 5-10 business days.
- Trucks and other equipment such as pipes will be used during construction, and you may see open trench excavation and debris removal.
- Dust control will be provided in all project areas.
- Enclosures or other barriers will be used in construction areas wherever necessary for public safety.
- Flaggers will be used where traffic is impacted. Traffic will be restored to normal when construction has been completed at the end of each workday.
- Trash pickup, deliveries, access to businesses and residential driveways will be maintained.
- Parking may be temporarily restricted in some areas, and signs will be posted in advance telling you where and when.
- You will be notified 24-48 hours in advance whenever sewer services may be temporarily interrupted.
|