ABOUT THE CITY'S SEWER SYSTEM
CURRENT SEWER CONSTRUCTION PROJECTS
  Air Treatment Facility - La Cienega and Jefferson
  Avenue 45 – Arroyo Drive Relief Sewer
  Lower North Outfall Sewer Rehabilitation Project
  Lower North Outfall Sewer Rehabilitation Project –Phase 2
Silver Lake Area Sewer Replacement Project
The Secondary Sewer Renewal Program (SSRP)
Beverlywood Street and I-10 Freeway Sewer Rehabilitation Project
Golden State and I-10 Freeway Sewer Rehabilitation Project
  Imperial Highway and Figueroa Street Sewer Rehabilitation Project
  Laurel Canyon Boulevard and Mulholland Drive Sewer Rehabilitation Project
Lincoln Boulevard and Sunset Avenue Sewer Replacement Project
Mandeville Canyon Road and Westridge Road Sewer Rehabilitation Project
Rodeo Road – 52nd Street, and La Brea Avenue – Crenshaw Boulevard Sewer Rehabilitation Project
Soto Street and
I-10 Freeway Sewer Rehabilitation Project
COMPLETED SEWER CONSTRUCTION PROJECTS
LATERAL ROOT NOTIFICATION PROGRAM
FATS, OIL AND GREASE PROGRAM
SPILLS & BACKWATER VALVES
ODORS

 
Project Information from the Bureau of Engineering

City Sewers Current Construction

Beverlywood Street and I-10 Freeway Sewer Rehabilitation Project

In November 2007, sewer pipe rehabilitation work is scheduled to begin in in West Los Angeles. The approximate boundary of the project is Beverlywood St. on the north, Bagley Ave. on the east, Overland Ave. on the west, and the Santa Monica Freeway on the south.


QUICK FACTS

  • About 2.5 miles of eight-inch diameter sewer pipes will be rehabilitated, or removed and replaced.
  • Ten existing maintenance holes will be upgraded.
  • Construction period: November 2007 through May 2009. Weather or other circumstances could shift the work schedule. Neighbors will be informed as conditions warrant.
  • Construction will generally take place Monday through Friday, from 8:00 a.m. until 5:30 p.m., and on major streets from 9:00 a.m. until 3:00 p.m to minimize traffic impacts.
  • Estimated Cost: $2,000,000.
  • Construction methods will include sewer pipe lining (rehabilitates defective sewers without excavation and surface disruption), and sewer pipe removal and replacement (performed by “open cut” or trenching, a method that is typically used where sewers are shallow).
  • In order to minimize disruption on your street, most of the construction work at each location will be completed in about 5-10 business days.
  • Trucks and other equipment such as pipes will be used during construction, and you may see open trench excavation and debris removal.
  • Dust control will be provided in all project areas.
  • Enclosures or other barriers will be used in construction areas wherever necessary for public safety.
  • Flaggers will be used where traffic is impacted. Traffic will be restored to normal when construction has been completed at the end of each workday. Trash pickup, deliveries, access to businesses and residential driveways will be maintained.
  • Parking may be temporarily restricted in some areas, and signs will be posted in advance telling you where and when.
  • You will be notified 24-48 hours in advance whenever sewer services may be temporarily interrupted.

 


 
CONTACT  AND  INFORMATION
Report Sewer ODORS
Report Sewer SPILLS   Or CALL 311, or (213) 473-3231
More information: (213) 978-0333,
or email pao@lacity.org
City of Los AngelesDepartment of Public Works  BUREAU OF SANITATION
 BUREAU OF ENGINEERING
 CONTRACT ADMINISTRATION