- Construction method: open trench
- Construction period: February 2008 - winter 2009
- 3,100 linear feet of 18” diameter sewer
- Project cost: $2.8 million
- Work will take place on portions of Lincoln Ave., Ave. 54, Buchanan St., and Ave. 56
- Twelve new maintenance holes will be built
- Construction will generally take place Monday through Friday, from 7:00 a.m. until 4:00 p.m.
- Some service interruptions may take place when the residential sewers are reconnected to the new sewer – residents will be notified 24 to 48 hours in advance
- Traffic and parking controls will be in effect - parking signs will be posted and flaggers will be used where traffic is impacted
- Safe and adequate pedestrian and vehicle access will be maintained at all times to residences, businesses and fire hydrants
- Each trench will be completed in 10 to 12 business days Trash pickup, deliveries, access to businesses and residential driveways will be maintained
|