Resurfacing & Construction Division
 
Resurfacing Friday Report
 
Zone I: Metro
September 11, 2005 -September 17, 2005
Projects Completed
Naomi Ave., 25th St. to 28th St.
SLAC
29th St., Naomi Ave. to Central Ave.
SLAC
108th St., Towne Ave. to San Pedro St.
SLAC
108th St., San Pedro St. to Main St.
SLAC
17th St., Gaffey St. to Cabrillo Ave.
HAC
Ross Pl., Fries Ave. to Island Ave.
SLAC
Denker Ave., 220th St. to Plaza Del Amo
HAC
59th St., Figueroa St. to Hoover St.
SLAC
60th St., Menlo Ave. to Vermont Ave.
SLAC
60th St., Hoover St. to Menlo Ave.
SLAC
Centre St., 9th St. to 11th St.
HAC
Redondo Blvd., 20th St. to 21st St.
WLAC
Thurman Ave., Venice Blvd. to I80' S/o Venice Blvd.
WLAC
Nicolet Ave., Martin Luther King, Jr. to Coliseum St.
SLAC
Centerline Miles Paved: 2.12
Lane Miles Paved: 6.46




Weekend Projects Completed
None    
Weekend Centerline Miles Paved: 0.00
Weekend Lane Miles Paved: 0.00




Specials
None  
Special Miles Paved: 0.00




Total Centerline Miles Paved: 2.12
Total Lane Miles Paved: 6.46







Equipment Problems
 
Large Profilers Midsize Profilers Small Profilers Skiploaders
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
Pavers Rollers Graders R.T. Loaders
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
Track Loaders Backhoes Gradals  
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 

Personnel Problems: None

Other Problems: None

 