Resurfacing Friday Report
Zone I: Metro
September 12, 2004 - September 18, 2004
| Projects
Completed |
| 228th St., CL E/o Frampton Ave. to Western Ave. |
SLAC |
| Capitol Dr., Gaffey St. to Amelia St. |
HAC |
| Alley W/o Meyler St., 7th St. to 8th St. |
HAC |
| Alley W/o Gaffey St., 11th St. to 12th St. |
HAC |
| Alley W/o Pacific Ave., 170' S/o 12th St. to 13th St. |
HAC |
| Centerline
Miles Paved: 1.19 |
| Lane
Miles Paved: 4.51 |
| Weekend
Projects Completed |
| None |
|
|
| Weekend
Centerline Miles Paved: 0.00 |
| Weekend
Lane Miles Paved: 0.00 |
| Specials |
| None |
|
|
| Special
Miles Paved: 0.00 |
|
Total Centerline Miles Paved:
1.19
|
|
Total Lane Miles Paved: 4.51
|
Equipment Problems
| Large
Profilers |
Midsize
Profilers |
Small
Profilers |
Skiploaders |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| Pavers |
Rollers |
Graders |
R.T.
Loaders |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| Track
Loaders |
Backhoes |
Gradals |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| |
| |
Personnel Problems: None
Other Problems: None
|
|