Resurfacing Friday Report
Zone I: Metro
September 5, 2004 - September 11, 2004
| Projects
Completed |
| Alley W/o Mesa St., 9th St. to 10th St. |
HAC |
| Lombardy Blvd., Eastern Ave. to Alhambra Ave. |
EAC |
| 3rd St., Lorena St. to DE W/o Fresno St. |
CAC |
| Centerline
Miles Paved: 0.84 |
| Lane
Miles Paved: 3.06 |
| Weekend
Projects Completed |
| None |
|
|
| Weekend
Centerline Miles Paved: 0.00 |
| Weekend
Lane Miles Paved: 0.00 |
| Specials |
| 159 w. Avenue 27 Intersection Barranca Ave. |
LAR |
9/8/04 |
| Special
Miles Paved: 0.00 |
|
Total Centerline Miles Paved:
0.84
|
|
Total Lane Miles Paved: 3.06
|
Equipment Problems
| Large
Profilers |
Midsize
Profilers |
Small
Profilers |
Skiploaders |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| Pavers |
Rollers |
Graders |
R.T.
Loaders |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| Track
Loaders |
Backhoes |
Gradals |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| |
| |
Personnel Problems: None
Other Problems: None
|
|