Resurfacing & Construction Division
 
Resurfacing Friday Report
 
Zone I: Metro
November 13, 2005 -November 19, 2005
Projects Completed
Vendome St., Temple St. to Beverly Blvd.
CAC
8th St., Hauser Blvd. to Fairfax Ave.
CAC
111th St., Wilmington Ave. to Willowbrook Ave.
SLAC
Willowbrook Ave., Wilmington Ave. to Imperial Hwy.
SLAC
Baldwin St., Thomas St. to Griffin Ave.
EAC
Centerline Miles Paved: 1.41
Lane Miles Paved: 5.13




Weekend Projects Completed
10th St. , Lemon St. to Wilson St.
11/19/05
CAC
14th St., Santa Clara St. to Wilson St.
11/19/05
CAC
6th St., 170' W/o Anderson St. to Mission Rd.
11/19/05
EAC
Weekend Centerline Miles Paved: 0.28
Weekend Lane Miles Paved: 0.60




Specials
Barrett Rd., Hall St. to Huntington Dr. North
11/19/05
EAC
Special Miles Paved: 0.00




Total Centerline Miles Paved: 1.69
Total Lane Miles Paved: 5.73







Equipment Problems
 
Large Profilers Midsize Profilers Small Profilers Skiploaders
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
Pavers Rollers Graders R.T. Loaders
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
Track Loaders Backhoes Gradals  
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 

Personnel Problems: None

Other Problems: None

 
Bureau of Street Services
Department of Public Works - City of Los Angeles