Resurfacing & Construction Division
 
Resurfacing Friday Report
 
Zone I: Metro
November 28, 2004 - December 4, 2004
Projects Completed
Alley N/o Exposition Blvd., DE E/o Kelton Ave. to Kelton Ave.
WLAC
Truxton Ave., Manchester Ave. to La Tijera Blvd.
WLAC
Opp St., Avalon Blvd. to Wilmington Blvd.
HAC
Centerline Miles Paved: 0.79
Lane Miles Paved: 2.71




Weekend Projects Completed
None    
Weekend Centerline Miles Paved: 0.00
Weekend Lane Miles Paved: 0.00




Specials
None  
Special Miles Paved: 0.00




Total Centerline Miles Paved: 0.79
Total Lane Miles Paved: 2.71







Equipment Problems
 
Large Profilers Midsize Profilers Small Profilers Skiploaders
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
Pavers Rollers Graders R.T. Loaders
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
Track Loaders Backhoes Gradals  
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 

Personnel Problems: None

Other Problems: None

 