Resurfacing & Construction Division
 
Resurfacing Friday Report
 
Zone I: Metro
February 26, 2006 - March 04, 2006
Projects Completed
133rd St., Hoover St. to Vermont Ave.
SLAC
Tamarind Ave., Sunset Blvd. to Fountain Ave.
CAC
Carlos Ave., Gower St. to Vista Del Mar
CAC
Selma Ave., El Centro Ave. to Vine St.
CAC
Selma Ave., Ivar Ave. to Las Palmas Ave.
CAC
14th St. Pl., Main St. to Broadway
CAC
Figueroa Ter., 382' W/o Colledge St. to Colledge St.
CAC
Linda Rosa Ave., Avoca St. to Loleta Ave.
ELAC
Argus Dr., Colorada Blvd. to Chicksaw Ave.
ELAC
Selma Ave., Courtney Ave. to Fairfax Ave.
WLAC
Ave 5 7, 460' W/o Eaton St. to Highgate Ave.
ELAC
Alley S/o 41st St., St. Andrews Pl. to Gramercy Pl.
SLAC
Centerline Miles Paved: 2.33
Lane Miles Paved: 6.34




Weekend Projects Completed
Vermont Ave., Hollywood Blvd, to Barndall Ave.
02/26/06
CAC
Sierra St., Mercury Ave. to Flora Ave.
03/04/06
ELAC
Weekend Centerline Miles Paved: 0.44
Weekend Lane Miles Paved: 2.43




Specials
None
Special Miles Paved: 0.00




Total Centerline Miles Paved: 2.77
Total Lane Miles Paved: 8.77







Equipment Problems
 
Large Profilers Midsize Profilers Small Profilers Skiploaders
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
Pavers Rollers Graders R.T. Loaders
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
Track Loaders Backhoes Gradals  
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 

Personnel Problems: None

Other Problems: None

 