Projects Completed
2nd St., Beaudry Ave. to Emerald St./Bixel St.
WLAC
Academy Rd., Stadium Way to Park Dr.
SLAC
Morton Pl., Park Dr. to Morton Ave.
SLAC
L St., Figureoa St. to DE W/o Figueroa St.
HAC
Malabar St., Indiana St. to Sloat St.
SLAC
Norwood St., Washington Blvd. to 23rd St.
SLAC
36th St., 6th Ave. to 11th Ave.
SLAC
Centerline Miles Paved: 1.78
Lane Miles Paved: 6.04




Weekend Projects Completed
Olympic Blvd., Ellwood St. to Alameda St. 3/20/05 CAC
Schrader Blvd., Hollywood Blvd. to Sunset Blvd. 3/20/05 CAC
Vermont Ave., Washington Blvd. to Adams Blvd. 3/26/05 SLAC
Weekend Centerline Miles Paved: 0.94
Weekend Lane Miles Paved: 4.52




Specials
None  
Special Miles Paved: 0.00




Total Centerline Miles Paved: 2.72
Total Lane Miles Paved: 10.56







Equipment Problems
 
Large Profilers Midsize Profilers Small Profilers Skiploaders
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
Pavers Rollers Graders R.T. Loaders
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
Track Loaders Backhoes Gradals  
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 

Personnel Problems: None

Other Problems: None

 