Resurfacing & Construction Division
 
Resurfacing Friday Report
 
Zone I: Metro
February 27, 2005 - March 5, 2005
Projects Completed
Laveta Te., Scott Ave. to Sunset Blvd.
HAC
Centerline Miles Paved: 0.34
Lane Miles Paved: 1.07




Weekend Projects Completed
None    
Weekend Centerline Miles Paved: 0.00
Weekend Lane Miles Paved: 0.00




Specials
Whalers Walk 03/03/05
HAC
Watchorn Walk 03/03/05
HAC
Special Miles Paved: 0.22




Total Centerline Miles Paved: 0.34
Total Lane Miles Paved: 1.07







Equipment Problems
 
Large Profilers Midsize Profilers Small Profilers Skiploaders
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
Pavers Rollers Graders R.T. Loaders
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
Track Loaders Backhoes Gradals  
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 

Personnel Problems: None

Other Problems: None

 
Bureau of Street Services
Department of Public Works - City of Los Angeles