Resurfacing Friday Report
Zone I: Metro
June 11, 2006 -June 17, 2006
| Projects
Completed |
| Broadway, Jefferson Blvd. to 37th St. |
SLAC |
| 164th St., Menlo Ave. to Vennont Ave. |
SLAC |
| 164th St., Estrella Ave. to Orchard Ave. |
HAC |
| 32nd St., Central Ave. to San Pedro St. |
SLAC |
| 238thS t., DE e/o President Ave. to President Ave. |
HAC |
| Wadsworth Ave., 32nd St. to JeffersonB lvd. |
SLAC |
| 33rd St., Boaz St. to Central Ave. |
SLAC |
| Folsom St., Evergreen Ave. to Forest Ave. |
ELAC |
| Winter St., Blades St. to Mott St. |
ELAC |
| 25th St., Hooper St. to Central Ave. |
SLAC |
| 23rd St., Gramercy Pl. to DE w/o Cimarron St. |
SLAC |
| Dillion St., Sayre Ln. (Pvt) to Marathon St. |
CAC |
| Centerline
Miles Paved: 2.26 |
| Lane
Miles Paved: 7.79 |
| Weekend
Projects Completed |
| San Pedro St., 7th St. to 9th St. |
06/11/06 |
ELAC |
| San Vicente Bl., E/Rdwy, Burton Wy to Colgate Ave. |
06/17/06 |
SLAC |
| San Viecnte Bl., W/Rdwy, Button Wy to CL s/o La Cienega Bl. |
06/17/06 |
SLAC |
| Burton Wy, N/Rdwy, La Cienega Bl/San Vicente Bl. to Robertson |
06/17/06 |
SLAC |
| Weekend
Centerline Miles Paved: 0.85 |
| Weekend
Lane Miles Paved: 3.71 |
| Specials |
| None |
|
|
| Special
Miles Paved: 0.00 |
|
Total Centerline Miles Paved:
3.11
|
|
Total Lane Miles Paved: 11.50
|
Equipment Problems
| Large
Profilers |
Midsize
Profilers |
Small
Profilers |
Skiploaders |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| Pavers |
Rollers |
Graders |
R.T.
Loaders |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| Track
Loaders |
Backhoes |
Gradals |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| |
| |
Personnel Problems: None
Other Problems: None
|
|