Resurfacing & Construction Division
 
Resurfacing Friday Report
 
Zone I: Metro
June 5, 2005 -June 11, 2005
Projects Completed
Alley N/o 89th St., De E/o Broadway to Alley E/o Broadway
SLAC
Colton St., Boylston St. to Toluca St.
CAC
Jasmine Ave., Venice Blvd. to CL S/o Venice Blvd.
WLAC
Ave. 16, Albion st. to DE E/o Alvion St.
ELAC
Santa Fe Ave., 7th St. to Olympic Blvd.
CAC
252nd St., Petroleum Ave. to Normandie Ave.
HAC
254th St., Petroleum Ave. to Normandie Ave.
HAC
Alley S/0 76th St., Alley W/o figueroa St. to Hoover St.
SLAC
Centerline Miles Paved: 1.82
Lane Miles Paved: 5.85




Weekend Projects Completed
None    
Weekend Centerline Miles Paved: 0.54
Weekend Lane Miles Paved: 2.30




Specials
None  
Special Miles Paved: 0.00




Total Centerline Miles Paved: 1.82
Total Lane Miles Paved: 5.85







Equipment Problems
 
Large Profilers Midsize Profilers Small Profilers Skiploaders
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
Pavers Rollers Graders R.T. Loaders
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
Track Loaders Backhoes Gradals  
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 

Personnel Problems: None

Other Problems: None

 
Bureau of Street Services
Department of Public Works - City of Los Angeles