Resurfacing Friday Report
Zone I: Metro
June 27, 2004 - July 3, 2004
| Projects
Completed |
| 82nd St., Central Ave. to Avalon Bl. |
HAC |
| Buckingham Rd., 30th St. to Exposition Bl. |
SLAC |
| Centerline
Miles Paved: 0.75 |
| Lane
Miles Paved: 2.14 |
| Weekend
Projects Completed |
| None |
|
|
| Weekend
Centerline Miles Paved: 0.00 |
| Weekend
Lane Miles Paved: 0.00 |
| Specials |
| None |
|
|
| Special
Miles Paved: 0.00 |
|
Total Centerline Miles Paved:
0.75
|
|
Total Lane Miles Paved: 2.14
|
Equipment Problems
| Large
Profilers |
Midsize
Profilers |
Small
Profilers |
Skiploaders |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| Pavers |
Rollers |
Graders |
R.T.
Loaders |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| Track
Loaders |
Backhoes |
Gradals |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| |
| |
Personnel Problems: None