Resurfacing & Construction Division
 
Resurfacing Friday Report
 
Zone I: Metro
July 3, 2005 -July 9, 2005
Projects Completed
Oxford Ave., 6th St. to wilshire Blvd.
CAC
McDonald Ave., Opp St. to Anaheim St.
HAC
8th St., N/Rdwy, Oxford Ave. to Western Ave.
CAC
8th St., s/Rdwy, Oxford Ave. to Western Ave.
CAC
8th St., Fedrora St. to Oxford Ave.
CAC
Alley W/o Cloverdale, Alley S.o Pico Blvd. to Venice Blvd.
CAC
F St., Lakme Ave. to Broad Ave.
HAC
Centerline Miles Paved: 1.27
Lane Miles Paved: 5.00




Weekend Projects Completed
None    
Weekend Centerline Miles Paved: 0.00
Weekend Lane Miles Paved: 0.00




Specials
Fleet St., DE E/o Canal St. to Pacific Ave. WLAC
7/5/05
Galleon St., De E/o Canal St. to Pacific Ave, WLAC
7/5/05
Canal Court, Fleet St. to Galleon St. WLAC
7/5/05
Special Miles Paved: 0.21




Total Centerline Miles Paved: 1.27
Total Lane Miles Paved: 5.00







Equipment Problems
 
Large Profilers Midsize Profilers Small Profilers Skiploaders
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
Pavers Rollers Graders R.T. Loaders
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
Track Loaders Backhoes Gradals  
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 

Personnel Problems: None

Other Problems: None

 
Bureau of Street Services
Department of Public Works - City of Los Angeles