Resurfacing Friday Report
Zone I: Metro
January 17, 2006 -January 21, 2006
| Projects
Completed |
| York Blvd., Avenue 55 to Avenue 50 |
ELAC |
| York Blvd., Aldama St. to Avenue 55 |
ELAC |
| Lynnfield St., Buday Ave. to Chadwick Dr. |
ELAC |
| Chester St., Buday Ave. to Chadwick Dr. |
ELAC |
| 41st Pl., San Pedro St. to Main St. |
WLAC |
| Manhatten Pl., Melrose Ave. to D/E S/o Clinton St. |
WLAC |
| Clinton Ave., Western Ave. to Wilton Pl. |
WLAC |
| Ridgewood Pl., Elmwood Ave. to Beverly Blvd. |
WLAC |
| Centerline
Miles Paved: 2.10 |
| Lane
Miles Paved: 8.18 |
| Weekend
Projects Completed |
| None |
|
|
| Weekend
Centerline Miles Paved: 0.00 |
| Weekend
Lane Miles Paved: 0.00 |
| Specials |
| 62nd St., 240' W/o St. Andrews Pl. to 239' E/o Gramercy Pl. |
1/03/06 |
SLAC |
| Special
Miles Paved: 0.00 |
|
Total Centerline Miles Paved:
2.10
|
|
Total Lane Miles Paved: 8.18
|
Equipment Problems
| Large
Profilers |
Midsize
Profilers |
Small
Profilers |
Skiploaders |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| Pavers |
Rollers |
Graders |
R.T.
Loaders |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| Track
Loaders |
Backhoes |
Gradals |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| |
| |
Personnel Problems: None
Other Problems: None
|
|