Resurfacing & Construction Division
 
Resurfacing Friday Report
 
Zone I: Metro
January 9, 2005 - January 15, 2005
Projects Completed
Adams Blvd., 7th Ave. to Montclair St.
CAC
Selby Ave., Exposition Blvd. to Clarkson Rd/Malcom Ave.
WLAC
Exposition Blvd., Overland Ave. to Selby Ave.
WLAC
Otay Dr., DE N/o Cleland Ave. to Cleland Ave.
EAC
Cleland Ave., Tacuba St. to Otay Dr.
EAC
Centerline Miles Paved: 0.90
Lane Miles Paved: 3.50




Weekend Projects Completed
None    
Weekend Centerline Miles Paved: 0.00
Weekend Lane Miles Paved: 0.00




Specials
None  
Special Miles Paved: 0.00




Total Centerline Miles Paved: 0.90
Total Lane Miles Paved: 3.50







Equipment Problems
 
Large Profilers Midsize Profilers Small Profilers Skiploaders
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
Pavers Rollers Graders R.T. Loaders
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
Track Loaders Backhoes Gradals  
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 

Personnel Problems: None

Other Problems: None

 