Resurfacing & Construction Division
 
Resurfacing Friday Report
 
Zone I: Metro
February 12, 2006 - February 18, 2006
Projects Completed
80th Pl., Emerson Ave. to Dunbarton Ave.
WLAC
80th Pl., McConnell Ave. to Creighton Ave.
WLAC
Turquoise St., Beagle St. to DE Wlo Huntington Dr.
ELAC
82nd St., Gramercy Pl. to Van Ness Ave.
WLAC
83rd St., Main St. to Broadway
SLAC
58th Pl., Budlong Ave. to Normandie Ave.
SLAC
45th St., Flower St. to Figueroa St.
SLAC
43rd St., Figueroa St. to Hoover St.
SLAC
Avenue 35, 100' Wlo Verdugo Rd. to Verdugo Rd.
ELAC
Centerline Miles Paved: 1.48
Lane Miles Paved: 4.67




Weekend Projects Completed
National BI., Castle Highs Av. to Exposition Bl/Palms Ct.
02/12/06
CAC
62nd St., Central Ave. to Avalon Blvd.
02/18/06
SLAC
Weekend Centerline Miles Paved: 0.28
Weekend Lane Miles Paved: 1.53




Specials
None
Special Miles Paved: 0.00




Total Centerline Miles Paved: 1.76
Total Lane Miles Paved: 6.20







Equipment Problems
 
Large Profilers Midsize Profilers Small Profilers Skiploaders
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
Pavers Rollers Graders R.T. Loaders
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
Track Loaders Backhoes Gradals  
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 

Personnel Problems: None

Other Problems: None

 
Bureau of Street Services
Department of Public Works - City of Los Angeles