Resurfacing & Construction Division
 
Resurfacing Friday Report
 
Zone I: Metro
February 15, 2004 - February 21, 2004
Projects Completed
Olympic Bl., Western Ave. to Arlington Ave.
CAC
Barrywood Ave., D/E N/o Burhugh Pl. to Capitol Dr.
HAC
Redondo Bl., Apple St. to Adams Bl.
CAC
Centerline Miles Paved: 0.82
Lane Miles Paved: 3.96




Weekend Projects Completed
None    
Weekend Centerline Miles Paved: 0.00
Weekend Lane Miles Paved: 0.00




Specials
None    
Special Miles Paved: 0.00




Total Centerline Miles Paved: 0.82
Total Lane Miles Paved: 3.96







Equipment Problems
 
Large Profilers Midsize Profilers Small Profilers Skiploaders
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
Pavers Rollers Graders R.T. Loaders
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
Track Loaders Backhoes Gradals  
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 

Personnel Problems: None

Other Problems: None

 
Bureau of Street Services
Department of Public Works - City of Los Angeles