Resurfacing & Construction Division
 
Resurfacing Friday Report
 
Zone I: Metro
December 11, 2005 -December 17, 2005
Projects Completed
Alexandria Ave., Sunset Blvd. to Fountain Ave.
CAC
Lemon Grove Ave., Kingsley Dr. to Hobart Ave.
CAC
Mildred Ave., Venice Blvd. to Pacific Ave.
WLAC
75th St., Main St. to Grand Ave.
SLAC
Packard St., Fairfax Ave .to Crescent Heights Blvd.
CAC
Randolph Ave., DE N/o Cudahy St. to Cudahy St.
SLAC
42nd St., Main St. to Broadway
SLAC
42nd St., Broadway to Grand Ave.
SLAC
42nd St., Flower St. to Figueroa St.
SLAC
Centerline Miles Paved: 1.67
Lane Miles Paved: 4.63




Weekend Projects Completed
None
Weekend Centerline Miles Paved: 0.00
Weekend Lane Miles Paved: 0.00




Specials
60th St., Western Ave. to Gramercy Pl.
12/11/05
SLAC
Special Miles Paved: 0.00




Total Centerline Miles Paved: 1.67
Total Lane Miles Paved: 4.63







Equipment Problems
 
Large Profilers Midsize Profilers Small Profilers Skiploaders
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
Pavers Rollers Graders R.T. Loaders
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
Track Loaders Backhoes Gradals  
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 

Personnel Problems: None

Other Problems: None

 
Bureau of Street Services
Department of Public Works - City of Los Angeles