Resurfacing Friday Report
Zone I: Metro
December 12, 2004 - December 18, 2004
| Projects
Completed |
| Laurel Ave., Melrose Ave. to Bevely Blvd. |
CAC |
| Via Marisol, Lomitas Dr. to Via Arbolada |
EAC |
| Centerline
Miles Paved: 1.11 |
| Lane
Miles Paved: 4.73 |
| Weekend
Projects Completed |
| None |
|
|
| Weekend
Centerline Miles Paved: 0.00 |
| Weekend
Lane Miles Paved: 0.00 |
| Specials |
| Maple Ave., Washington Blvd. to 23rd St. |
|
12/16/04 |
| Special
Miles Paved: 0.29 |
|
Total Centerline Miles Paved:
1.11
|
|
Total Lane Miles Paved: 4.73
|
Equipment Problems
| Large
Profilers |
Midsize
Profilers |
Small
Profilers |
Skiploaders |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| Pavers |
Rollers |
Graders |
R.T.
Loaders |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| Track
Loaders |
Backhoes |
Gradals |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| |
| |
Personnel Problems: None
Other Problems: None
|
|