Resurfacing Friday Report
Zone I: Metro
August 15, 2004 - August 21, 2004
| Projects
Completed |
| Alley S/o 111th Pl., Alley W/o Monitor Ave. to Graham Ave. |
SLAC |
| Alley S/o 112th St., Graham Ave. to Maie Ave. |
SLAC |
| Alley S/o 112th St. Maie Ave. to Compton Ave. |
SLAC |
| Alley S/o 111th Pl., Graham Ave. to Maie Ave. |
SLAC |
| 111th St., Santa Ana Blvd. South to Croesus Ave. |
SLAC |
| Vista Del Mar, Imperial Hwy. to CL S/o Grand Ave. |
WLAC |
| Centerline
Miles Paved: 1.57 |
| Lane
Miles Paved: 6.27 |
| Weekend
Projects Completed |
| None |
|
|
| Weekend
Centerline Miles Paved: 0.00 |
| Weekend
Lane Miles Paved: 0.00 |
| Specials |
| None |
|
|
| Special
Miles Paved: 0.00 |
|
Total Centerline Miles Paved:
1.57
|
|
Total Lane Miles Paved: 6.27
|
Equipment Problems
| Large
Profilers |
Midsize
Profilers |
Small
Profilers |
Skiploaders |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| Pavers |
Rollers |
Graders |
R.T.
Loaders |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| Track
Loaders |
Backhoes |
Gradals |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| |
| |
Personnel Problems: None