Resurfacing & Construction Division
 
Resurfacing Friday Report
 
Zone I: Metro
August 15, 2004 - August 21, 2004
Projects Completed
Alley S/o 111th Pl., Alley W/o Monitor Ave. to Graham Ave.
SLAC
Alley S/o 112th St., Graham Ave. to Maie Ave.
SLAC
Alley S/o 112th St. Maie Ave. to Compton Ave.
SLAC
Alley S/o 111th Pl., Graham Ave. to Maie Ave.
SLAC
111th St., Santa Ana Blvd. South to Croesus Ave.
SLAC
Vista Del Mar, Imperial Hwy. to CL S/o Grand Ave.
WLAC
Centerline Miles Paved: 1.57
Lane Miles Paved: 6.27




Weekend Projects Completed
None    
Weekend Centerline Miles Paved: 0.00
Weekend Lane Miles Paved: 0.00




Specials
None  
Special Miles Paved: 0.00




Total Centerline Miles Paved: 1.57
Total Lane Miles Paved: 6.27







Equipment Problems
 
Large Profilers Midsize Profilers Small Profilers Skiploaders
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
Pavers Rollers Graders R.T. Loaders
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
Track Loaders Backhoes Gradals  
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 

Personnel Problems: None

Other Problems: None

 
Bureau of Street Services
Department of Public Works - City of Los Angeles