Resurfacing & Construction Division
 
Resurfacing Friday Report
 
Zone I: Metro
August 8, 2004 - August 15, 2004
Projects Completed
Sardis Ave., Barry Ave. to Barrington Ave.
WLAC
Bolker Pl., DE N/o Barhugh Pl. to Barhugh Pl.
HAC
Casey Pl. to Westmont Dr., to Barhugh Pl.
HAC
Bejay Pl., Barrywood Ave. to Taper Ave.
HAC
78th St., Vermont Ave. to Raymond Ave.
SLAC
78th St., Raymond Ave. to Normandie Ave.
SLAC
Eastman Pl., Barrywood Ave. to Taper Ave.
HAC
Barhugh Pl., Barrywood Ave. to Taper Ave.
HAC
Centerline Miles Paved: 1.27
Lane Miles Paved: 3.53




Weekend Projects Completed
None    
Weekend Centerline Miles Paved: 0.00
Weekend Lane Miles Paved: 0.00




Specials
None  
Special Miles Paved: 0.00




Total Centerline Miles Paved: 1.27
Total Lane Miles Paved: 3.53







Equipment Problems
 
Large Profilers Midsize Profilers Small Profilers Skiploaders
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
Pavers Rollers Graders R.T. Loaders
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
Track Loaders Backhoes Gradals  
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 

Personnel Problems: None

Other Problems: None

 
Bureau of Street Services
Department of Public Works - City of Los Angeles