Resurfacing Friday Report
Zone I: Valley
April 9, 2006 -April 15, 2006
| Projects
Completed |
| Cloverdale Ave., 350' s/o Packard St. to Pico Blvd. |
CAC |
| 46th St., Normandie Ave. to Denker Ave. |
CAC |
| Lincoln High Dr., DE n/o Lincoln High Dr. to North Broadway |
ELAC |
| Lincoln High Pl., DE n/o Lincoln High Dr. to Lincoln High Dr. |
ELAC |
| Sycamore Ave., San Vicente Blvd. to Pico Blvd. |
CAC |
| Orange Dr., San Vicente Blvd. to Pico Blvd. |
CAC |
| Spaulding Ave., Wiloughby Ave. to Melrose Ave. |
CAC |
| Mansfield Ave., San Vicente Blvd. to Pico Blvd. |
CAC |
| Tremaine Ave., San Vicente Blvd. to Pico Blvd. |
CAC |
| Longwood Ave., San Vicente Blvd. to Pico Blvd. |
CAC |
| Edgewood Pl., Tremaine Ave. to Highland Ave. |
CAC |
| Edgewood Pl., Rimpau Blvd. to Tremaine Ave. |
CAC |
| Crenshaw Blvd. E/Service Rd., 39th St. to Crenshaw Blvd. |
SLAC |
| 46th St., McKinley Ave. to Avalon Blvd. |
SLAC |
| Centerline
Miles Paved: 2.50 |
| Lane
Miles Paved: 6.72 |
| Weekend
Projects Completed |
| 80th St., Hoover St. to Vermont Ave. |
04/09/06 |
SLAC |
| 80th St., Figueroa St. to Hoover St. |
04/09/06 |
SLAC |
| 74th St., Central Ave. to Avalon Blvd. |
04/15/06 |
SLAC |
| 74th St., Avalon Blvd. to San Pedro St. |
4/15/06 |
SLAC |
| Weekend
Centerline Miles Paved: 1.18 |
| Weekend
Lane Miles Paved: 3.26 |
| Specials |
| None |
|
|
Special
Miles Paved: 0.00 |
|
Total Centerline Miles Paved:
3.68
|
|
Total Lane Miles Paved: 9.98
|
Equipment Problems
| Large
Profilers |
Midsize
Profilers |
Small
Profilers |
Skiploaders |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| Pavers |
Rollers |
Graders |
R.T.
Loaders |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| Track
Loaders |
Backhoes |
Gradals |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| |
| |
Personnel Problems: None
Other Problems: None
|
|