Resurfacing & Construction Division
 
Resurfacing Friday Report
 
Zone I: Metro
April 24, 2005 -April 30, 2005
Projects Completed
Short Ave., Centinela Ave. to Alla Rd.
WLAC
Mindanao Way, Alla Rd. to Glencoe Ave.
WLAC
Alla Rd., Short Ave. to Bonaporte Ave.
WLAC
Alley W/o Leimert Blvd., Stocker St. to Creed Ave.
SLAC
Alley W/o Gramercy Pl., 48th St. to 52nd St.
SLAC
Centerline Miles Paved: 1.64
Lane Miles Paved: 6.59




Weekend Projects Completed
Tracy St., Saint George St. to Talmadge St. 4/30/05 CAC
Rowena St., Hyperion Ave. to Saint George St. 4/30/05 CAC
Weekend Centerline Miles Paved: 0.51
Weekend Lane Miles Paved: 1.74




Specials
None  
Special Miles Paved: 0.00




Total Centerline Miles Paved: 2.15
Total Lane Miles Paved: 8.33







Equipment Problems
 
Large Profilers Midsize Profilers Small Profilers Skiploaders
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
Pavers Rollers Graders R.T. Loaders
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
Track Loaders Backhoes Gradals  
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 

Personnel Problems: None

Other Problems: None

 
Bureau of Street Services