Resurfacing Friday Report
Zone I: Metro
April 10, 2005 -April 16, 2005
| Projects
Completed |
| Castle Heights Pl., Beverlywood St. to Castle Heights Ave. |
WLAC |
| Machester Ave. N/Rdwy., Avalon Blvd. to Wall St. |
SLAC |
| Manchester Ave. S/Rdwy., Avalon Blvd. to Wall St. |
SLAC |
| Park Grove Ave., Washington Blvd. to 23rd St. |
SLAC |
| Benton Way, 3rd St. to 6th St. |
CAC |
| Normandie Ave., Martin L. King Blvd. to Vernon Ave. |
SLAC |
| Centerline
Miles Paved: 1.75 |
| Lane
Miles Paved: 6.15 |
| Weekend
Projects Completed |
| Cesar E. Chavez Ave., Saint Louis St. to State St. |
4/10/05 |
EAC |
| Raymond Ave., Florence Ave. to DE S/o 78th St. |
4/16/05 |
SLAC |
| Weekend
Centerline Miles Paved: 0.62 |
| Weekend
Lane Miles Paved: 2.07 |
| Specials |
| None |
|
|
| Special
Miles Paved: 0.00 |
|
Total Centerline Miles Paved:
2.37
|
|
Total Lane Miles Paved: 8.22
|
Equipment Problems
| Large
Profilers |
Midsize
Profilers |
Small
Profilers |
Skiploaders |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| Pavers |
Rollers |
Graders |
R.T.
Loaders |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| Track
Loaders |
Backhoes |
Gradals |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| |
| |
Personnel Problems: None
Other Problems: None
|
|