Resurfacing & Construction Division
 
Resurfacing Friday Report
 
Zone I: Metro
April 10, 2005 -April 16, 2005
Projects Completed
Castle Heights Pl., Beverlywood St. to Castle Heights Ave.
WLAC
Machester Ave. N/Rdwy., Avalon Blvd. to Wall St.
SLAC
Manchester Ave. S/Rdwy., Avalon Blvd. to Wall St.
SLAC
Park Grove Ave., Washington Blvd. to 23rd St.
SLAC
Benton Way, 3rd St. to 6th St.
CAC
Normandie Ave., Martin L. King Blvd. to Vernon Ave.
SLAC
Centerline Miles Paved: 1.75
Lane Miles Paved: 6.15




Weekend Projects Completed
Cesar E. Chavez Ave., Saint Louis St. to State St. 4/10/05 EAC
Raymond Ave., Florence Ave. to DE S/o 78th St. 4/16/05 SLAC
Weekend Centerline Miles Paved: 0.62
Weekend Lane Miles Paved: 2.07




Specials
None  
Special Miles Paved: 0.00




Total Centerline Miles Paved: 2.37
Total Lane Miles Paved: 8.22







Equipment Problems
 
Large Profilers Midsize Profilers Small Profilers Skiploaders
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
Pavers Rollers Graders R.T. Loaders
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
Track Loaders Backhoes Gradals  
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 

Personnel Problems: None

Other Problems: None

 
Bureau of Street Services
Department of Public Works - City of Los Angeles