Resurfacing & Construction Division
 
Resurfacing Friday Report
 
Zone I: Metro
April 25, 2004 - May 1, 2004
Projects Completed
Avenue 45, Toland Way to York Blvd.
EAC
Morton Pl. North, Park Dr. to Morton Ave.
EAC
Las Flores Dr., Hill Dr. to Eagle Vista Dr.
EAC
North Main St., Wilhardt St. to Alhambra/Vignes St.
EAC
Vermont Ave., E/Rdwy., 120th St., to El Segundo Blvd.
SLA
Rose Ave., Veteran Ave. to Greenfield Ave.
WLA
McDuff St., Scott Ave. to La Veta Terrace
EAC
Centerline Miles Paved: 1.77
Lane Miles Paved: 6.37




Weekend Projects Completed
None    
Weekend Centerline Miles Paved: 0.00
Weekend Lane Miles Paved: 0.00




Specials
None  
Special Miles Paved: 0.00




Total Centerline Miles Paved: 1.77
Total Lane Miles Paved: 6.37







Equipment Problems
 
Large Profilers Midsize Profilers Small Profilers Skiploaders
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
Pavers Rollers Graders R.T. Loaders
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
Track Loaders Backhoes Gradals  
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 

Personnel Problems: None

Other Problems: None

 
Bureau of Street Services
Department of Public Works - City of Los Angeles